Cleanouts for building sewers should be installed on any turn that is more than how many degrees?

Study for the California Pipeline Contractor (C-34 License) Exam. Utilize interactive flashcards and multiple-choice questions with hints and explanations. Prepare thoroughly for your exam!

Multiple Choice

Cleanouts for building sewers should be installed on any turn that is more than how many degrees?

Explanation:
Access points are placed where a sewer line changes direction so a plumber can insert a snake and clear a blockage. When a turn is larger than 135 degrees, the bend becomes too tight for standard rodding tools to negotiate effectively, so a cleanout is needed at that location to provide direct access for cleaning. Turns of 135 degrees or less can usually be cleared through the existing run with the tool, so no extra cleanout is required there. That’s why the correct threshold is 135 degrees.

Access points are placed where a sewer line changes direction so a plumber can insert a snake and clear a blockage. When a turn is larger than 135 degrees, the bend becomes too tight for standard rodding tools to negotiate effectively, so a cleanout is needed at that location to provide direct access for cleaning. Turns of 135 degrees or less can usually be cleared through the existing run with the tool, so no extra cleanout is required there. That’s why the correct threshold is 135 degrees.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy